The Project
Decommission & Relocation of Perry Barr
Scope of Works
- Severn Trent were re-developing the building the antennas were positioned on.
- The equipment room did not form part of the development area and would remain in situ.
- Our client had a stub mast located on the building which was shared with another operator.
- The short-term solution was to remove all active equipment from the building on to a temporary structure and re-jig into the existing equipment room.
- Works had to be completed on or before 6th April, 2018
Site Overview
The antennas were located on a building and the kit was situated in a ground-based, brick-built equipment room which was approximately 60 metres to the South East.
Proposed Solution
- We created a bespoke design for the temporary tower base using concrete ballast blocks due to its small footprint (4m x 4m)
- Critical to project success was working closely with the Other Licensed Operator (OLO) to ensure that the project ran to timescales.
- Deploy a 15m temp mast adjacent to the existing equipment room.
- Remove the antennas from the current site and re-rig them onto the new temporary structure. Run feeders into the existing equipment room.
- Space was limited and the only option available for the new structure was an old cabin base. The dimensions were only 4m x 4m.
- A temporary structure was sourced at short notice that would fit on the base.
- Due to the space restrictions an ‘ad hoc’ design was required. Clarke Telecom structural engineers produced a solution whereby concrete blocks were added as ballast to ensure the stability of the tower.
Challenges Overcome
Timeframes
Three-week project including Easter weekend site shutdown
Severe Weather
Heavy snowfall and high winds
STW Proceedures
RAMS / POW needed STW approval prior to site start
Site Conditions
The building the antennas were located on was part of an underground reservoir which restricted size / positioning of crane.
“Excellent work all round… A total re-design for a site solution within the timeframes left to meet the Drop Dead Date, giving us at best 6 weeks”
– Client Estates Surveyor
Project Information
Location: Birmingham
Project Duration: 2 months
"The programme was continually adjusted to mitigate delays due to severe weather and Easter holidays to deliver to the client’s tight timelines"